Well, I'm gaining a little traction on my project once again since my initial set backs.
I fired Contractor #1 that was supposed to do the complete project and hired another Contractor that's done some work for me in the past to fix Contractor #1's mistakes along with finishing up the project. In all, that will set me back another $10-12K but such is life since I'm stuck with an incomplete building. No other way out other than to spend money. :smiley_blackeye:
I'm now waiting in line for Contractor #2 as he's working on jobs ahead of me. Meanwhile my sheet metal is sitting in mud puddles after 10" of rain in the past 10 days and my steel main frame work is beginning to rust. :smiley_badmood:
Contractor #2 says he should be available in about another 7-10 days after he completes a 14,000 square foot structure in Pittsburgh. He can't come over soon enough.
Given, I'm now way over budget. Meanwhile I've had some free time while I'm waiting so I finished off the rough grade/slopes around my structure, added gravel backfill around the perimeter, and finished pouring concrete under the overhang (with the help of a friend).
Here we are now. I can't wait to put this project behind me.