Footers and 12 piers poured yesterday. It took 36 yards to complete the task.
"The Man Cave" will be delivered Thursday on a flatbed from Colorado.
 

Attachments

  • Footer Pour.jpg
    Footer Pour.jpg
    258 KB · Views: 211
  • Footer Complete.jpg
    Footer Complete.jpg
    266.1 KB · Views: 173
Last edited:

Buckmaster

Senior Member
14,537
205
Portage
You going to pour the floor? Heat it if you do?

Yes, I have 1,800 foot of 1/2 Pex to zip tie to the wire mesh above 4" gravel and 1 1/4" Barrier floor insulation. It will be encompassed within the 6" floor.
I will have 6 (300 foot loops) radiant heat zones within the floor.
 

Buckmaster

Senior Member
14,537
205
Portage
The framework should be completed and plum today.
Saturday and Monday will be spent tensioning 700+ fastener assemblies.
Concrete floor to be poured sometime next week.
 

Attachments

  • Barn 3.jpg
    Barn 3.jpg
    267.4 KB · Views: 183
Last edited:

Milo

Tatonka guide.
8,189
171
Ben take lots of pics for me on the floor. I want to do the same thing with my barn..